Posted by Charles J. Doane on SAILfeed

shenan.01

AS I NOTED in my last post on the loss of HMS Bounty during Hurricane Sandy, one of the big unanswered questions is: why was the ship taking on so much water? That she was leaking enough to sink is especially puzzling in that just 11 days earlier she’d been relaunched at Boothbay Harbor Shipyard in Maine (see photo up top) after spending a month in drydock for repairs. It may or may not be relevant, but my eyebrows did rise up a bit when I learned this week that the very same yard got dinged in federal court earlier this year for over $400K in damages for shoddy work performed on Shenandoah, a 108-foot schooner, back in 2008.

And it seems we are talking extremely shoddy work here. According to the final judgment entered by U.S. District Court judge George O’Toole in Massachusetts on March 30, the defects in Boothbay Harbor’s work included “among other things, missing bungs, empty fastener holes, improperly installed fasteners, use of an improper sealant, overly wide caulking seams, poorly installed caulking, and too-short futtock overlaps.”

Less than a month after Boothbay Harbor finished refastening and partially replanking Shenandoah‘s hull in May 2008, the boat started leaking massively. An initial inspection turned up a four-foot section of seam with no caulking in it. Later, after a much more thorough review, it was found that literally hundreds of bungs in the boat’s hull had no fasteners under them, that several seams were not caulked or were poorly caulked, and that the deck had been sealed with window glazing instead a proper marine sealant.

post continues here